New Rossano-Sibari line

Calabria, southern Italy, 2022-2024

Client ANAS Spa

In the framework of the modernization of the S.S. 106 Jonica, the new infrastructural link has been developed on new aligment to reach better levels of resilience of the existing north-south network, providing a viable alternative to the parallel A2 motorway on the Tyrrhenian front. The project involves the construction of a new road of “B” class according to the 2001 Decree, in the section between the Viaduct Coserie in the territory of Corigliano-Rossano and the SS534 Firmo-Sibari in the territory of Cassano allo Jonio. The project is completed by the upgrading on site of the SS534 for an extension of about 6 km between Megalotto 3 (road junction not included) and the intersection with the existing SS106 Radd. The route consists of a total length of about 32km, 5 km developed on viaducts.

E.D.IN., within the scope of the Technical and Economic Feasibility Design for D&B tendering, has been responsible for the structural and geotechnical design of about 20 dual and single carriageway viaducts along the new link. The structures comprise composite steel-concrete decks, bow-tie steel arch bridges and extradosed steel trusses.

Infrastrutture Stradali Nuovo collegamento Rossano-Sibari 1
Infrastrutture Stradali Nuovo collegamento Rossano-Sibari 2
Infrastrutture Stradali Nuovo collegamento Rossano-Sibari 3
Infrastrutture Stradali Nuovo collegamento Rossano-Sibari 4

New Catanzaro-Crotone line

Calabria, southern Italy, 2022-2024

Client ANAS Spa

In the framework of the modernization of the S.S. 106 Jonica, the new infrastructural link has been developed on a new aligment, to reach better levels of resilience of the existing north-south network, providing a viable alternative for the parallel A2 motorway on the Tyrrhenian front. In the development of the new route between the cities of Catanzaro and Crotone, the new link extends for about 50km, along which one finds about 20km of different structures, including tunnels and viaducts, for a total investment cost of about 2 billion euros.

E.D.IN., within the scope of the Technical and Economic Feasibility Design for D&B tendering, has been responsible for the structural and geotechnical design of about  40 separate dual carriageway viaducts along the new link. The structures consist of composite steel-concrete decks, with seismic protection provided by latest generation isolation systems.

Infrastrutture Stradali Nuovo collegamento Catanzaro-Crotone 1
Infrastrutture Stradali - Nuovo collegamento Catanzaro-Crotone 2
Infrastrutture Stradali - Nuovo collegamento Catanzaro-Crotone 3

New High Speed Line Salerno-Reggio Calabria

Campania-Calabria, southern Italy, 2021-2022

Client Italferr S.p.A.

Engineering services for the technical-economic feasibility design of lots 1A Battipaglia-Romagnano (34 km), 1B Romagnano-Buonabitacolo (49 km), and 1C Buonabitacolo-Praia (45 km). E.D.IN. developed the design of the railway viaducts for a total of 30 structures with an overall extension of over 30 km and a total of 780 single and double track spans. The activities carried out included the study of viaduct layouts in relation to hydraulic and road interferences and the morphology of the territory, the sizing of typical substructures, deep foundations on piles and shafts and typical temporary works. The project envisages a number of different structural types, starting with conventional filler beam decks with spans of about 20 m and precast pre-stressed concrete girders with spans of 25 m. Within the project, in the presence of widespread interferences and flood areas, composite steel-concrete decks were also consistently adopted with spans of 40 m and 45 m with 4 I-beams and spans from 50 m to 75 m with box girders. Additionally, steel trusses are adopted for single track spans between 60 m and 75m and, finally, special structures, such as steel tied arch bridges with spans up to 120m, are planned for the crossings of the A2 “Mediterranean” Motorway, providing landmark elements characterizing the entire project.

EDIN Infrastrutture Ferroviarie - Nuova linea AV Salerno-Reggio Calabria 2
EDIN Infrastrutture Ferroviarie - Nuova linea AV Salerno-Reggio Calabria 3
EDIN Infrastrutture Ferroviarie - Nuova linea AV Salerno-Reggio Calabria 1

Verona-Padova High Speed Line

Veneto, northern Italy, 2022-2023

Client IRICAV 2 Consortium

In the framework of the design of the high speed railway line Verona – Padova, lot 1 (1st and 2nd sub-lots Verona – Montebello Vicentino and Montebello Vicentino – Bivio Vicenza) E.D.In has developed the Detailed Design of 12 viaducts for an overall extension of about 7000m. Main structures of the project include viaducts on the Fibbio and Alpone rivers, of 2380 and 1770m long respective lenghts.  The decks are of prestressed concrete for spans of 25m, composite steel-concrete for spans from 40 to 46m and filler beams with spans up to 22m. The piers are box shaped with rounded edges, while abutments have a standard geometry. All foundations stand on large diameter piles.

EDIN Infrastrutture Ferroviarie - Linea AV/AC Verona-Padova 2
EDIN Infrastrutture Ferroviarie - Linea AV/AC Verona-Padova 3
EDIN Infrastrutture Ferroviarie - Linea AV/AC Verona-Padova 4

Iraq NS RW Project

Iraq, 2022 – in progress

Client BTP Inc.

The “Development Road” project consists in the new Railway & Highway Systems (i.e. a multimodal corridor of almost 1,200 km in length), aimed to connect the new Grand Faw Port up to the Turkish Border and enhance the socio-economic development of Iraq. The new Railway system shall be designed in order to transport passengers at 300 km/h and freights at 120 km/h, while serving most of the Iraqi cities from South to North. Main structures of the railway include typical spans of 25m in prestressed concrete, composite steel-concrete decks for 40m and 50m spans as well as steel trusses for 70m spans. Special structures within the Project include a steel tied arch bridge with a 100m span and a cable stayed bridge with a total length of 400m and a main span of 200m. Within the project, E.D.IN. has developed the Feasibility Study and Preliminary Design of all the Railway and Highway bridges and viaducts as well as minor structures such as overpasses and underpasses.

EDIN Infrastrutture Ferroviarie - Iraq NS RW Project 1
EDIN Infrastrutture Ferroviarie - Iraq NS RW Project 2
EDIN Infrastrutture Ferroviarie - Iraq NS RW Project 3
EDIN Infrastrutture Ferroviarie - Iraq NS RW Project 4
EDIN Infrastrutture Ferroviarie - Iraq NS RW Project 5

Sotra Fjord Bridge

Norway, in progress

Client Sotra Link Consortium

The Sotra suspension bridge, main span 608m, is the main crossing within a large infrastructural project linking the town of Bergen to the Sotra island. The scope of work comprises the consultancy for the structural design of the bridge and of its access viaducts, with independent FEM of its global behaviour, including the erection stages. To point out that the project is one of the first developed “BIM only”, with no 2D or paper drawings.

EDIN Ponti Sospesi - Ponte sul fiordo del Sotra 1
EDIN Ponti Sospesi - Ponte sul fiordo del Sotra 2
EDIN Ponti Sospesi - Ponte sul fiordo del Sotra 3
EDIN Ponti Sospesi - Ponte sul fiordo del Sotra 4

Ramp 1B, Umm Lafina Project

UAE, 2022

Client WeBuild Inc.

The Ramp 1B flyover is part of a large infrastructural project ancillary to the Abu Dhabi – Dubai motorway link. The structure features a segmental box prestressed concrete deck with five continuous spans, maximum span length 114 m. The scope of work followed a number of issued occurred during the last construction stages and comprised the consultancy for the evaluation of the phenomena and for the rehabilitation design, numerical analyses of the erection stages with simulation of the damage and of the subsequent measures.

EDIN Infrastrutture Stradali - Umm Lafina 2
EDIN Infrastrutture Stradali - Umm Lafina 3
EDIN Infrastrutture Stradali - Umm Lafina 1
EDIN Infrastrutture Stradali - Umm Lafina 4

Crossing of the Po River

Cremona, Italy, 2022

Client Itinera Inc.

The bridge is part of the detail design of the motorway segment comprising the new Castelvetro toll area, the connection with the SS 10 “Padana Inferiore” road and the completion of the motorway link to the SS 234 road. The main crossing shows a bow-tie steel arch bridge with “network” hangers system, span 200m, with access viaducts featuring steel-concrete composite continuous girders of span from 50 to 75 m, for a total length of about 2 km.    

EDIN Ponti ad Arco - Attraversamento del Po 1
EDIN Ponti ad Arco - Attraversamento del Po 2
EDIN Ponti ad Arco - Attraversamento del Po 3

Braila Suspension Bridge

Braila, Romania, 2015, 2018-2023

Client CNAIR, Association Webuild-IHI

The suspension bridge on the Danube at Braila, located not far from the river delta, is the main crossing in an important North-South road link of local and transnational relevance. Opened in June 2023, with its 1120 m of main span and a total length of 2204,3 m is one of the largest in Europe and the largest in Central-Southern Europe. In 2015 E.D.In. prepared the feasibility design of the structures of the bridge with Client CNAIR, the Romanian road authority. Later, in 2018-2023 carried out the engineering services for the structural design, including design for approval, final design and construction drawings with Client the General Contractor, the Italian-Japanese Association Webuild S.p.A.-Ishikawajima-Harima Heavy Industries Co. Ltd. The concrete structures of the bridge have been awarded the 2022 AICAP prize as the best concrete structures with Italian involvement of the previous two-year-period.

F. Brancaleoni, CONCEPTS AND NEW PERSPECTIVESFOR LONG SPAN BRIDGES Keynote Lecture, CAR International Conference, Bucharest, 9 – 11 July 2015.

F. Brancaleoni, PONTE SOSPESO DI BRAILA, ROMANIA: MODELLAZIONE NUMERICA GLOBALE E LOCALE, Convegno “Processi innovativi digitali per i Ponti e le Infrastrutture”, Rome, 2019.

F. Brancaleoni, M. Averardi Ripari, G. Carrapetta, D. Caschera, A. Del Vecchio, T. Idani, A. Minniti, T. Shima, IL PONTE SOSPESO SUL DANUBIO A BRAILA, PROGETTO E STATO ATTUALE, Costruzioni Metalliche, 2022.

F. Brancaleoni, L. Bonomo, G. Carrapetta, G. De Santis, A. Minniti, LE STRUTTURE IN CALCESTRUZZO PER IL PONTE SOSPESO SUL DANUBIO A BRAILA, Atti Italian Concrete Conference 2022, Neaples, 2022.

F. Brancaleoni, M. Averardi Ripari, IL CALCESTRUZZO NEI PONTI SOSPESI, Invited Lecture, Atti Italian Concrete Conference 2024, Florence, 2024.

Braila 1a
DCIM102MEDIADJI 0359.JPG
Braila 2
Braila 3
Braila 4
Braila 5
Braila 6
Braila 7
Braila 8
Braila 9
Braila 10
Braila 11
Foto A Pagina Intera

EDIN S.r.l.

E.D.IN. Ltd.
Consulting Engineers

Via Casilina, 3/t
00182 - ROMA
Phone.: +39 06 5452591
Fax.: +39 06 54525939
Email: info@ediningegneria.com
Vat Number: 01275921003
Codice Fiscale: 04016070585


Copyright Edin Ltd